Firmware Updates and Release Notes

Commercial Inverters (with SetApp)

Firmware Version: 4.20.514

Release Date: April 2024

This release supports Three Phase Commercial Inverters and Three Phase Commercial Inverters with Synergy Technology. 

Impacted Products and Software

ProductsCPUDSP1DSP2Additional
SE25K-SE33.3K Three Phase Commercial Inverter4.20.5141.13.23052.19.1900 
SE20K-SE40K Three Phase Commercial Inverter with PNs SExxK-xxxxIxxxx 4.20.5141.20.19282.20.1514 
SE50K-SE100K Three Phase Inverter with Synergy Technology4.20.5141.13.23052.19.1900 
SE50K-SE120K Three Phase Inverter with Synergy Technology (up to 120kW), with PNs SExxK-xxxxIxxxx4.20.5141.20.19282.20.1514Synergy Manager:
0.4.11 / 1.1.10


Devices' Firmware Versions

ProductCPUControllerAdditional
SolarEdge Revenue Grade Meter
SE-MTR-3Y-400V-B
0.2020 2.19.1900

New Features and Enhancements

Reduced P_OK time for Power Optimizers - Global Release

Significantly reduced the detection (P_OK) time for Power Optimizers when performed during site commissioning. The detection process is now much quicker than before and finishes as soon as the expected number of Power Optimizers is successfully detected (taking only several minutes on average but not longer than 10 minutes).

To support this improvement, a new step was added to the SetApp Pairing process for installers to enter the expected number of Power Optimizers to be detected by each inverter. This helps installers validate that the process was successfully completed, and all units were connected while they’re still on-site, in case any issues arise.

Note: This upgrade is supported by all P and S-Series Power Optimizers out of the box.

* If the expected number of Power Optimizers is not entered, the detection process will finish after 10 minutes instead of only 3.
 

The revamped Power Optimizer detection flow is as follows:

To start the Power Optimizer Pairing and P_OK process, enter the 'Pairing' option via the SetApp main menu and tap ‘Start Pairing’.

From the new ‘Optimizers Number’ window, enter the number of expected Power Optimizers to be paired. 

  • For Three Phase Inverters:

    pairing
     
  • For Synergy Inverters, enter the number of Power Optimizers per Synergy unit (as shown in the example below for a 2-unit Synergy inverter
    pairing1
     
  • Power Optimizer pairing is then performed as before, and after this stage is complete inverter production will begin:

    pairing2
     
  • The Power Optimizer detection process is complete once the expected number of units has been reached:
    pairing3
     

If there is a mismatch between the expected and the actual detection of Power optimizers, there can be several potential results from the detection process:

  • If the expected number of Power Optimizers is not entered (or was set to zero): the Power Optimizer count times out after 10 minutes (the maximum count time allowed).
  • If the expected number of Power Optimizers entered is lower than the detected number: the installer will be notified that the pairing process was successfully completed once the expected number of Power Optimizers has been detected, and the Power Optimizer count will continue in the background until the actual detected number is reached.
  • If the expected number of Power Optimizers entered is higher than the detected number: the search to find the total number of expected Power Optimizers continues. This search times out after 10 minutes. The installer can then:
    Confirm that the detected number is the correct amount by tapping ‘It’s OK’ Or Tap ‘Re-pair’pairing4

Now Compatible for Commercial Installations: SolarEdge Home Hub Three Phase Inverters and SolarEdge Home Battery 48V - Europe Only

SolarEdge commercial sites can now be connected to the residential SolarEdge Home Hub Inverter - Three Phase and SolarEdge Home Battery 48V, enabling on-grid storage for the small-scale commercial market.

Read this App Note to learn more about configuring the SolarEdge Home Hub Solution for commercial site designs.


Country Table Updates

Germany: updated German grid code names:

Existing NameNew Name
003 - GermanyGermany 4105
038 - Germany MVGCGermany 4110
089 - Germany MV 480VGermany 4110 480V

 

  • Germany: Added P(f) underflow options for 4110 grid codes
  • New Caledonia: New grid codes were updated to align with local regulations
  • Slovakia - Update Slovakia parameters


Known Issues and Limitations

  • IEEE 1547 register map 703 mismatch:
    • Max/Min wakeup grid voltage in SetApp doesn't match the Modbus register (which displays the value in relation to V nominal)
    • Workaround: To match the values, the following calculation must be performed:
      • (Max. Grid Voltage / V nominal) * 100)
      • Expected fix: 4.21.5xx
  • Optimizers P_OK and status list is populated after performing a Factory Reset. After the Factory Reset, P_OK increases and the Power Optimizers status list in SetApp is also populated with the previously paired Power Optimizers
    • Workaround: After pairing is performed, the correct values will appear
  • Commercial Three Phase Inverters: when enabled, the inverter’s Active Export limit isn't updated to the SetApp status/site/limit field. However, the Active Export feature continues to function normally as configured

Latest Firmware Version: 4.19.521

Release Date: November 2023

This release supports Three Phase Commercial Inverters and Three Phase Commercial Inverters with Synergy Technology.

Released Firmware Versions

ProductCPUDSP1DSP2Additional
Three Phase Commercial Inverter4.19.5211.13.22122.19.1806 
Three Phase Commercial Inverter
with PNs SExxK-xxxxIxxxx
4.19.5211.20.16482.20.1307 
Three Phase Inverter with Synergy Technology4.19.5211.13.22122.19.1806 
Three Phase Inverter with Synergy Technology
(up to 120kW) with
PNs SExxK-xxxxIxxxx
4.19.5211.20.16482.20.1307Synergy Manager:
0.4.9 / 1.1.9

 

New Features and Enhancements

  • SolarEdge Sense Connect
    • Sense Connect functionality is now supported on SolarEdge Three Phase 16K-17K inverters, protecting the PV Module (DC) side of the system. Power Optimizers continuously monitor the connector temperature on their short input and output cables and inform the inverter of any abnormal temperature increase so it can react accordingly.
    • SetApp – Power Optimizer serial number is now displayed on Sense Connect alerts
  • Potential Induced Degradation (PID)
    • The ability to enable PID mitigation remotely is now supported for Three Phase Synergy Technology inverters via the Monitoring Platform. Go to the ‘Remote Settings’ menu in the Monitoring Platform’s ‘Admin’ tab to toggle the inverter’s PID Mitigation settings. Learn more here 
  • SetApp Interface Updates
    • SetApp PID Activation menu: users can now differentiate between the built-in SolarEdge PID solution and an external third-party PID device
       SetApp PID Activation menu
    • Status SetApp page for Commercial inverters: added Sac, I1, I2, I3, V12, V23, V31 measurements as follows:

      Previous Screen
       image
      Updated Screen
      Updated Screen
    • SetApp Language Configuration
      • Language configuration is now performed via “SetApp side menu > Settings > Locale”, instead of via the “Commissioning > Country and Language” menu
        SetApp Language Configuration
  • Zero-Export Limitation
    • SolarEdge inverters are now compliant with UNE217001: 2020-10 and Spain ITC-BT-40 (RD 244/2019) zero export to grid regulations. 

Country Table Updates 

CountryIssue Description
Korea

Added new grid code for Korea (800Vdc).

A SE33.3K inverter with DCD will require a fixed string voltage of
800Vdc to allow a 2-string design with S1200 Power Optimizers.

AustraliaTo avoid installer confusion, the name for ‘Old’ Australia grid codes was changed to ‘Obsolete’. 
France

Existing country code was m odified to Cosphi = 1:

  • France (Cosphi = 1) and France MV (Cosphi = 1)

The following new grid codes for power configuration were created:

  • France (Coshpi = -0.94) and France MV (Cosphi = -0.94)
Czech RepublicAdded new Czech inverter settings in accordance with ‘CEZ Distribuce’ defined thresholds
Japan

Updated display names of grid codes for Japan:

  • Code 26: "Japan 50Hz" => "Japan 1ph 202V L-N  / 3ph 350V L-L 50Hz"
  • Code 27: "Japan 60Hz" => "Japan 1ph 202V L-N  / 3ph 350V L-L 60Hz"
SloveniaCountry code updated to support type A certification 

Austria

R25 - Austria Country Table updated

Austria

R25 - PT1 time constant tau for Q(U) and P(V) is now available for installer input in the Power Control menus

Greece, Slovenia, Slovenia MV, France

Enabled Grid Protection settings

Vietnam

Modified Vietnam grid code to support requirements of sites > 500kW

Hungary

Updated parameters for Hungarian grid codes

Brazil

Updated parameters for Brazilian grid codes according to the national grid operator (ONS)

Norway

Updated Norwegian grid codes stage 1 frequency thresholds to:

  • 087 – Norway

  • 150 - Norway Delta

Italy

Split Italy country settings into three new settings in order to help installers correctly set frequency and voltage thresholds:

  • Italy 0-21 Low

  • Italy 0-21 High

 

Known Issues and Limitations

  • Optimizers P_OK and status list is populated after performing a Factory Reset. P_OK increases and the Power Optimizers status list in SetApp is also populated with the previously paired Power Optimizers
    • Workaround: After pairing is performed, the correct values will appear
  • Commercial Three Phase Inverters: when enabled, the inverter’s Active Export limit isn't updated to the SetApp status/site/limit field. However, the Active Export feature continues to function normally as configured
  • Central Settings (Leader, Follower): the Follower P(V) and Q(V) values are set to a different value than the Master.
    • Workaround: Perform Central Commissioning to restore the correct values to the Follower inverter

Version: 4.19.513

Release Date: August 2023

This release supports the UK PV market only.

With the introduction on May 1, 2023 of the new G100 Issue 2 Amendment 2 for the customer limiting scheme, SolarEdge residential and commercial products including PV inverters, batteries, and Smart Energy devices now fully comply with this latest G100 amendment.

Released Firmware Versions

ProductCPUDSP1DSP2Synergy Manager
Three Phase Commercial Inverter4.19.5131.20.16432.20.13050.3.8 / 1.1.9
Three Phase Commercial Inverter
with PNs SExxK-xxxxIxxxx
4.19.5131.13.22112.19.1806 
Three Phase Inverter with Synergy Technology4.19.5131.13.22112.19.1806 
Three Phase Inverter with Synergy Technology
(up to 120kW) with
PNs SExxK-xxxxIxxxx
4.19.5131.20.16432.20.1305 

 

New Features and Enhancements

G100 Introduction

EREC G100 Issue 2 supersedes EREC G100 Issue 1 Amendment 2 “Technical Requirements for Customers Export and Import Limitation Schemes” and became mandatory for sites commissioned after May 1, 2023. G100 Issue 2 requires control of the PV system such that the current flow levels at the grid connection point will remain within pre-configured boundaries. The current boundaries are set by the installers during the commissioning phase, according to the levels that were agreed upon in the Connection Agreement.

At the steady state, the inverter constantly monitors the current flow level at the grid connection point. It manages the production level and site consumption (by controlling the smart devices) to maintain the Import and Export values within the configured boundaries. G100 also defines a set of rules for entering the system into restricted operational modes in cases where the limitations were breached. If the system is operating in one of the restricted modes, installers will be able to set the system back to Normal mode.

G100 System Settings

System default current limits are as follows:

  • On Commercial sites, the Maximal Import Limit  (MIL) is equal to 60A and the Maximum Export Limit (MEL) is equal to 16A
  • Installers will be able to modify these default values using SetApp.

limit export

Operating in Restricted Mode

EREC G100 Issue 2 defines two levels of operation in restricted modes.
The first level (state 3) is caused due to multiple breaches of the limitations for more than 15 seconds or an excursion longer than 1 minute.
The second level (AKA Locked out mode) is caused by multiple entries into state 3.

Setting the system to Normal operation mode

If the system is in Restricted mode, installers can use SetApp to set the system back to Normal mode.

commissioning

Note: In Commercial sites, installers will not be able to set the system back to Normal operational mode within four hours of the start of state 3.

Additional Features
 

Feature Description

Added the String Toggle feature to SE33.3K/66.6K/100K inverters in Europe.
 
Users must confirm that they comply with the conditions which allow them to use 850Vdc.
 

String Toggle Feature | Added a pop-up message when selecting 850V in Europe.

Connected Inverter

 

UK Country Table Updates

Added G100 support.

 

 

Version: 4.18.514

Release Date: April 2023

This release supports Three Phase Commercial Inverters and Three Phase Commercial Inverters with Synergy Technology.

Released Firmware Version

Products CPU DSP1 DSP2 Additional
Three Phase Commercial Inverter 4.18.514 1.13.2115 2.19.1700  
Three Phase Commercial Inverter with PNs SExxK-xxxxIxxxx 4.18.514 1.20.1518 2.20.1200  
Three Phase Commercial Inverter with Synergy Technology 4.18.514 1.13.2115 2.19.1700  
Three Phase Commercial Inverter with
Synergy Technology: PNs SExxK-xxxxIxxxx
4.18.514 1.20.1518 2.20.1200 Synergy Manager:
0.3.7 / 1.0.8

 

New Features and Enhancements

  • Updated Japan Grid Codes for the new 25kW Commercial Three Phase Inverters: SE25K-JPI3IBNM4, SE25K-JPI6IBNM4
  • South Africa Grid Codes Frequency Start Parameter was modified to comply with grid code requirements, to avoid issues during commissioning or after a grid event
  • Lithuanian grid protection settings are now supported
  • Poland Grid Codes were updated
  • Uruguay country code was updated to comply with new reconnection time regulations
  • Tan phi change was implemented for all French Grid Codes in low voltage range (up to 500 kVA) to comply with new regulations

Known Issues and Limitations

  • Regarding the central settings (Leader inverter with Follower inverters), in some cases the country, grid and power values are not updated in the Follower inverters
    • Workaround: Try to configure the settings again
  • There is an error in the power limit display for the Three Phase Inverters with Synergy Technology (up to 120kW) during slow ramp up after a single Synergy Unit trips
     

Firmware Version: 4.17.615

Release Date: January 2023

This release supports all SetApp-enabled Three Phase Commercial Inverters and Three Phase Commercial Inverters with Synergy Technology.
 

Released Firmware Version

Products CPU DSP1 DSP2 Additional
Three Phase Commercial Inverter 4.17.615 1.13.2018 2.19.1602  
Three Phase Commercial Inverter with
PNs SExxK-xxxxIxxxx 
4.17.615 1.20.1230 2.20.906  
Three Phase Inverter with Synergy Technology 4.17.615 1.13.2018 2.19.1602  
Three Phase Inverter with Synergy Technology
(up to 120kW) with PNs SExxK-xxxxIxxxx
4.17.615 1.20.1230 2.20.906 Synergy Manager:
0.3.7 / 1.0.8

 

New Features and Enhancements

  • Firmware upgrades during site visits is now optional for inverters that were already commissioned and not connected to an Energy Meter. 
    • After connecting to the inverter using SetApp, if a new firmware version is available you may decide to delay the upgrade to a later time by tapping Skip Upgrade
    • Note: SolarEdge recommends upgrading inverter firmware whenever a new version is released
  • The SolarEdge Sense Connect feature is now supported on Three Phase Commercial Inverters and Three Phase Inverters with Synergy Technology, with DSP1 1.20.xxxx and DSP2 2.20.xxxx
    • Sense Connect enhances system safety through early detection and prevention of potential electric arcs at the connector level due to improper connections or possible malfunctions resulting from wear and tear
  • For ROW (i.e. all regions outside of Europe and North America), the ability to toggle the inverter fixed string voltage between 750V and 850V  is now supported via SetApp for the SE33.3K, SE66.6K and SE100K commercial inverters
    • Enables improved design flexibility with fewer strings, less cables/fuses and reduced BoS costs
    • Relevant for installations connected to the S1200 Commercial Power Optimizer, and only for specific inverter part numbers
    • Read this App Note to learn how to toggle the inverter fixed string voltage
  • For European countries, the FCR-D-Down capability was added for Three Phase Commercial Inverters with SE DSP. Controlled and managed by Grid Services.

Known Issues and Limitations

  • Three Phase Inverters with Synergy Technology (up to 120kW): Resetting the inverter during the Pre-Commissioning stage will shut down the system if the inverter is solar powered and a power bank is not connected
    • Workaround: If a reset is required, reconnect the power bank before resetting