SolarEdge Powers Savings Even When Form and Function Both Matter
Three Phase Synergy Inverters deliver $42k in savings while meeting strict aesthetic requirements for landmark Indiana carport installation
A leading financial company sought to demonstrate their commitment to ESG investing while reducing energy costs at their Carmel, Indiana office. With roof obstructions from HVAC installations, a carport solution offered the ideal opportunity to showcase sustainability to clients.
Solar One, a leading Developer in the U.S., specializes in delivering large, complex commercial and industrial projects. With roots in the Texas solar market, they’ve expanded across the U.S. by focusing on strong customer relationships through clear communication and top-shelf engineering.
HIGHLIGHTS: Commercial solar installations can meet stringent aesthetic requirements while delivering cost savings through intelligent inverter selection, BoS cost reduction, flexible design, and wire management optimization.
Balancing Aesthetics, Complexity, and Cost on a Large-Footprint Carport
This 2.5 MW carport installation presented multiple engineering and design challenges:
SolarEdge Three Phase Synergy Inverters + Optimized Wiring Architecture
Solar One designed a solution centered on SolarEdge SE120KUS Three Phase Synergy Inverters with module-level power optimizers, dramatically simplifying the wiring architecture while meeting all aesthetic and performance requirements.
Key features:
Significant Savings Without Compromising on Design Excellence
The financial company now operates a 2.5 MW solar carport that serves as a financial and ESG showcase. The table below quantifies the financial advantage of SolarEdge Three Phase Synergy Inverters over traditional string inverters.
Cost Comparison: SolarEdge Three Phase Synergy Inverter vs. Traditional String Inverter
|
Component |
SolarEdge Inverter |
String Inverter |
Savings |
|---|---|---|---|
|
DC String Conductors |
16,463 ft / $8,067 |
33,462 ft / $16,396 |
$8,329 |
|
AC Conductors |
51,377 ft / $66,276 |
60,934 ft / $70,074 |
$3,798 |
|
Labor Costs |
1,208 hours / $102,680 |
1,321 hours / $112,285 |
$12,654 |
| Total Costs |
$312,123 |
$353,960 |
$41,837 (12%), 1.7c/Wdc |
Additional key benefits include: